IT Deployment Plan Orchestrates "Go Live"
A high tech organization needed to synchronize tasks across a number of technical departments to ensure a smooth transition to a production environment. To do so, a daily plan was created and managed to guide efforts at a very detailed level.
ProjectLead facilitated a team of IT leaders from various departments to construct a master plan covering Go Live preparations and activities.
ProjectLead monitored and updated progress on the plan on a daily basis.
ProjectLead performed triage on issues as they arose and made sure all parties were kept informed on a real time basis.
RESULTS
Integrated Multiple Departments
One plan tied multiple departments to the same schedule and deliverables.
Right Level of Detail
Management at a very tactical level was necessary as Go Live got closer.
Everyone Informed
Daily project update meetings kept everyone current on progress and issues.